The challenge

Part One

Scope of work

Cathara Consulting was engaged to support the delivery of the a large program in the Health sector. The Program involved a cost of over $40 million over a three-year period, to deliver the Work Packages outlined below:

  • WP1 – Enterprise Compute, Storage and Managed Services – Replacement of existing services contained within DC facilities (co-location), infrastructure assets and managed service components of the incumbent contract and those managed by the organisation.
  • WP2 – Data Centre (DC) Connectivity Transitional Network Management and Gateway Services – Connection of the existing DCs used by the WA health system, including its legacy core network, to ICT DCs, Transitional Network Services and Internet Gateway Services.
  • WP3 – Network Connectivity Metropolitan and WA regional sites – Relocation of the WA health system owned and operated data carriage WAN services (metropolitan and regional) to the Core platform for the purposes of moving to a unified government communications network.

Transformational Activity – leveraging of foundational building blocks and building on these to provide transformational benefits, with high level planning, opportunity identification and significant implementation as part of the program.

The challenge
The challenge

PART TWO

Requirements

Similarities between those contracts and requirements set out in this request:

  • Commercial and Procurement support – Support during tender evaluation and contract negotiations.
  • Establishment of the Program Governance and Program Structure
  • Development of Program Plan, Resource Plan, Registers and reporting documents – Waterfall and Agile.
  • Change Management strategy, planning and framework.
  • Risks, Issues, Dependencies and Project CR managment.
  • Management to scope, timeline and budget.
  • Optimal use of resources across Work Packages .
  • Engagement with key stakeholders as required with expertise relating to planning and advisory related disciplines
  • Liaise with stakeholders to review and endorse deliverables.
The challenge
The Approach
The Result

PART THREE

Contract outcomes

Particularly outputs, savings, efficiencies etc:

  • Support during tender evaluation and contract negotiations.
  • Establishment of the Program Governance.
  • Development of Program Plan, Resource Plan, Registers and reporting documents (this has been treated as a Hybrid Program, with some stages being delivered under a Waterfall approach and others under an Agile one).
  • Risks, Issues, Dependencies and Project CR managment.
  • Completion of WP2 on time and budget.
  • Scoping of work grouped in WP1, incluiding the migration of more than one thousand apps to the Cloud.
  • Set up of Change Management Framework and Stakeholder Impact Analysis.
  • Compliance with guidelines established by governing bodies and organisations.
  • Negotiation with incumbent, vendors and services providers, HSPs, and external organisations impacted by the program.
The challenge

HOW WE TRANSFORM

THE RIGHT THING, THE RIGHT WAY, FIRST TIME

In any transformation, innovation is a key driver. Having a strong innovative culture can be the “make or break” of a transformation process. Since its inception, Cathara has been assisting clients on this journey.

The challenge

TESTIMONIALS

WHAT OUR CLIENTS SAY

The trust and confidence that Cathara’s staff have for them, their regular contact, and making themselves readilaccessible, results in their maintaining a close knowledge and awareness of project and account activities

Associate Director, Client Services Information Services, University of Western Australia
The challenge

LET’S TALK ABOUT

YOUR BUSINESS

If you would like to learn more about our services and how we can help you, please get in touch with us.